Location: maple valley, wa
Start/finish Date: August 23 - present
Contract: $2,257,257.00     
Description: This project consists of the creation of wetland along the Cedar River. The Work required to complete this project includes installing and maintaining temporary erosion and sediment control facilities; providing temporary traffic control; removing noxious weeds; clearing and grubbing; removing garbage and miscellaneous abandoned infrastructure from the Site; tree salvage; installing and maintaining temporary de-watering and isolation facilities; excavation of about 60,000 TCY and haul; wetland grading; wetland soil amendment; placing and anchoring large woody debris and wildlife habitat snags; and seeding and planting. The project duration allowed for 2 seasons, but ACI was able to substantially complete the project within 1 season.