Location: Maple Valley, wa - East side of cedar river
Start/finish Date: june 2022 - september 2022
Contract: $9,449,449.00
Description: The work consists of removing an existing rock armored levee, construction of a new levee setback with biorevetment scour protection. Work also includes excavation of a floodplain side channel, installation of 100+ engineered log jams (ELJ) in the floodplain and river channel, constructing an overflow culvert under the roadway, Landscaping Guardrail and Restoration. Major components of work were completed in one Summer Fish Window.