Location: Steilacoom, WA
Start/finish Date: March 2023 - june 2023
Contract: $805,805.00   
Description: The scope of work includes pavement restoration along Rainier Street from Union Avenue to Puyallup Street, approximately 2,520 LF, and involves pavement grinding, subgrade restoration, paving, curb ramp replacement, utility grade adjustments, replacement of utility covers and lids, channelization, and traffic control.

 

Location: Cispus River/Yellowjacket Creek (Near Camp Cispus)
Start/finish Date: June 2023 - september 2023
Contract: $697,358.20   
Description: This project consisted of the installation of 16 Apex Engineered Logs Jams and 11 Side Channel Roughness Engineered Log Jams along the channel of Yellowjacket Creek near the confluence of the Yellowjacket and Cispus River. This included installing timber piles to stabilize each of the ELJ’s, along with channel grading.

 

Location: Lake Sammamish State Park – Sunset beach
Start/finish Date: may 2023 - june 2024
Contract: $3,418,150.00  
Description: Installation of three picnic shelters and two pedestrian shelters with lighting, shelter power, site furnishings, fencing, plantings, and new sidewalk throughout.

 

Location: East Wenatchee, wa
Start/finish Date: june 2023 - december 2024
Contract: $6,723,723.00
Description: Sidewalks on both sides of the street with buffer strips; raised intersections; crosswalks and ADA ramps; illumination; storm drainage, utility adjustments, utility relocations, cement concrete driveways, HMA driveways, landscape, irrigation.

 

Location: Enumclaw, wa
Start/finish Date: june 2023 - december 2024
Contract: $2,975,401.65
Description: Excavation of new Boise Creek and Chappel Springs stream channel segments, construction of an earthen embankment, installation of engineered log structures, construction of three new permanent bridge crossings, invasive species control and riparian planting restoration work, fish exclusion, golf course irrigation system preservation and restoration, golf course green and tee box restoration, construction of new golf course tee boxes, chain link fence installation, golf course pathway restoration.

 

Location: maple valley, wa
Start/finish Date: August 2023
Contract: $2,257,257.00     
Description: This project consists of the creation of wetland along the Cedar River. The Work required to complete this project includes installing and maintaining temporary erosion and sediment control facilities; providing temporary traffic control; removing noxious weeds; clearing and grubbing; removing garbage and miscellaneous abandoned infrastructure from the Site; tree salvage; installing and maintaining temporary de-watering and isolation facilities; excavation of about 60,000 TCY and haul; wetland grading; wetland soil amendment; placing and anchoring large woody debris and wildlife habitat snags; and seeding and planting. The project duration allowed for 2 seasons, but ACI was able to substantially complete the project within 1 season.

 

Location: puyallup, wa
Start/finish Date: april 2024 - july 2024
Contract: $974,974.00
Description: Construction of new sidewalk on Wildwood Park Drive between 31st Ave SE and 26th Ave SE including construction of new stormwater infrastructure, paving, lighting system interconnect, and RRFB pedestrian crossing.

 

Location: lakewood, wa
Start/finish Date: december 2023 - august 2024
Contract: $1,477,477.00
Description: Convert gravel existing gravel parking lot to a paved parking lot with new lighting system, storm sewer, irrigation, and landscaping.