Location: bremerton, wa
Start/finish Date: june 2022 - December 2022
Contract: $2,498,498     
Description: This Contract provides for the improvement of two culverts located in Price Road and Brentwood Drive by replacing them with precast concrete voided slab girder bridges. The work includes, but is not limited to, temporary traffic control, temporary stream diversion, demolition, removal of the existing culverts and structure and obstructions, temporary access road, grading, concrete class 4000 for substructure, furnishing, installing and grouting precast concrete voided slab girders, reconstruction of the roadway with hot mix asphalt, pavement markings, guardrail, streambed aggregate, rock for erosion and scour protection, and landscape restoration.

 

Location: Maple Valley, wa - East side of cedar river
Start/finish Date: june 2022 - september 2022
Contract: $9,449,449.00
Description: The work consists of removing an existing rock armored levee, construction of a new levee setback with biorevetment scour protection. Work also includes excavation of a floodplain side channel, installation of 100+ engineered log jams (ELJ) in the floodplain and river channel, constructing an overflow culvert under the roadway, Landscaping Guardrail and Restoration.    Major components of work were completed in one Summer Fish Window.

 

Location: Maple Valley, wa
Start/finish Date: july 2022 - October 2022
Contract: $1,175,175
Description: The improvements will include construction of 675 feet of new roadway from 228th Avenue SE/228th Place SE to the SE 231st Street improvements constructed by MV Logistics and intersection improvements at the 228th Place SE/228th Avenue SE and SE 238th Street/228th Avenue SE intersections.

The work includes:

* New HMA for new roadway and bike lanes

* Curb, gutter, sidewalk and median

* Storm drain system

* Landscape and Irrigation

* Illumination

* Utility Conduits

* Channelization and signing

* Temporary traffic control during construction

* Other work necessary to complete the Work as specified and shown in the Contract Documents

 

Location: Olympia
Start/finish Date: December 2022 - January 2023
Contract: $867,530.90
Description: This project consists of pavement and concrete flatwork removal, cement concrete curb and sidewalk installation, signal system upgrades, asphalt pavement planing, HMA overlay, channelization, landscaping, and other work, all in accordance with the Contract.

 

Location: Lakewood
Start/finish Date: January 2023 - july 2023
Contract: $1,445,445.00
Description: This contract provides for the construction of: a concrete basketball court, precast concrete bicycle pump track, concrete curb, gutter and sidewalk, community garden, off-leash dog area, riparian planting, irrigation, wood, and chainlink fencing at Springbrook Park.