Location: : steilacoom, WA
Start/finish Date: may 2019 – December 2019
Contract: $2,942,942.00
Description: Project provides for excavation, pavement removal, grading, cement concrete curb and gutter, cement concrete sidewalks, driveways, storm system improvements, soldier pile walls, pedestrian railing, beam guardrail, rockeries, street lighting, electrical conduit and vaults, asphalt paving, planing, asphalt overlay, landscape restoration, channelization, and traffic control.

 

Location: AUBURN, Wa
Start Date: JUNE 2019
END Date: OCTOBER 2019
Contract: $1,309,309
Description: This project provides for the improvement of 55th Avenue and the Bingamon Creek Culvert in King County by clearing and grubbing, grading, surfacing, paving with HMA, culvert excavation, providing and installing a precast concrete box culvert, retaining wall excavation, installing structural earth retaining walls, channel excavation, relocating a tributary stream, erosion control, seeding and mulching, planting, paint stripe, streambed restoration.

 

Location: : lacey, WA
Start/finish Date: may 2019 – Octover 2021
Contract: $5,920,920.01
Description: Project provides for the reconstruction of approximately 3000 feet of College Street and 22nd Avenue to include a modern roundabout, private utilities joint trench, water, sewer, stormwater, traffic signal, flashing beacons, illumination, modern roundabout to include; stormwater, water, sewer, flashing beacons, illumination, and landscaping.

 

Location: : seattle, WA
Start/finish Date: august 2019 – december 2019
Contract: $5,999,287.28
Description: Construction of a transit center/hub for Expedia Group which involved demolition of an existing building/concrete/asphalt and installing new utilities, new concrete drive lanes, and a modular building.

 

Location: SR 520, Town of Hunts Point, City of Kirkland and City of Bellevue
Start/finish Date: august 2019 - september 2019
Contract: $1,177,177
Description: repair of existing culverts and STREAM-BEDS including selective pruning and clearing, STREAM-BED grading, STREAM-BED sediment, STREAM-BED cobbles, STREAM-BED boulders, installation and removal of temporary stream diversion systems, erosion and water pollution control, planting RESTORATION, traffic control.

 

Location: : bellevue, WA
Start/finish Date: may 2019 - february 2020
Contract: $2,709,892.50
Description: Construction of an engineered gravity block wall and soldier pile wall.

 

Location: : lacey, WA
Start/finish Date: june 2019 - February 2020
Contract: $4,142,142.00
Description: Project provides for planing, paving and channelization of College St SE from Mullen Rd SE to Rainier Rd SE and Yelm Highway SE from City limit lines on the west to Ruddell Rd SE to include; ADA curb ramps, median construction, flashing beacons, illumination, landscaping, and irrigation.

 

Location: : north bend, WA
Start/finish Date: july 2019 - december 2019
Contract: $2,154,154
Description: Construction of a new roundabout including install of storm, JUT, and a new WATER MAIN.

 

Location: orting, Wa
Start/finish Date: october 2019 - november 2019
Contract: $1,147,570
Description: Construction of approximately 1,500 linear feet of discontinuous setback revetment involving excavation, Logs, slash and Concrete Dolos.

RELATED LINKS:
https://piercecountywa.gov/3159/Puyallup-River-Flood-Protection-at-Orvil

 

Location: bellevue, Wa
Start/finish Date: august 2019 - september 2019
Contract: $1,532,532
Description: Remove dip in asphalt pavement at Lakemont Blvd and Golf Club Road, replace with CSBC, Geogrid, and new asphalt. Remove asphalt and install layers of Geofoam blocks and pave over with new asphalt at Lakemont Blvd and 164th Ave. Install new water main, channelization, and a mini-roundabout at 164th Ave and Newport Way.

 

Location: Sanderson Field, Shelton, WA
Start/finish Date: november 2019 - September 2020
Contract: $3,080,080
Description: Asphalt overlay of runway and taxiway pavement, approximately 67,800SY of asphalt milling and 10,800TN of asphalt paving. Upgrade and replace runway edge lighting system. upgrade permanent signage along runway and taxiways. install new runway and taxiway pavement markings per faa standards.

 

Location: Lacey, Wa
Start/finish Date: june 2020 - february 2021
Contract: $1,968,700
Description: 27 Lot residential housing plat complete including erosion control, logging, clearing, site grading, sewer, storm drainage, water, JUT trenching, streets, sidewalks, frontage improvements, lighting.

 

Location: silverdale, wa
Start/finish Date: september 2019 - december 2020
Contract: $2,732,250
Description: performing earthwork and underground UTILITY work for the harrison specialty care clinic. exporting 65,000+ tcy of dirt.

 

Location: Lacey, WA; Mullen Road Lacey City Limits to Carpenter Road
Start/finish Date: DECEMBER 2019 / September 2021
Contract: $9,467,467.00
Description: Major work items include: Pulverizing Existing Asphalt Pavement, 22,000 SY; Precast Reinf. Conc. Box Culvert; Crushed Surfacing Base Course, 11,300 Ton; HMA CL. ½ in PG 58H-22 Fiber Reinforced, 5,500 Ton; Schedule A Storm Sewer Pipe, 5,475 LF; Water Main, 5,830 LF; Force Main Sewer Pipe, 5,800 LF; Illumination System; Roundabout Construction.